A procurement and QC checklist for the documents that should arrive with a linear bearing, guideway or ball screw shipment: CMM dimensional reports, hardness data, lead accuracy reports, material certificates and third-party verification, plus how to read them and what to check on incoming goods.
A linear bearing inspection report is only useful if it proves something you can verify. Here is what a complete outgoing inspection package should contain, what each document actually establishes, and how to read it before the goods leave your receiving dock.
Most quality disputes over linear motion components do not start with a failed bearing. They start with a missing piece of paper: a drawing revision nobody compared against, a hardness value quoted verbally, a batch number that cannot be traced back to a heat number. The cure is to agree on the document package at the purchase order stage, not after the container arrives.
What a full package looks like. Xiamen Dongfeng Bearing includes the outgoing inspection documentation described below β CMM reports, hardness data and material certificates β in its standard outgoing package; the exact document list is confirmed on your order, and third-party verification such as SGS reports is arranged per order. All of it is backed by ISO 9001 certification and a 24-month warranty.
The five documents in a complete outgoing package
1. CMM dimensional report
A coordinate measuring machine report records measured values for the dimensions that matter, taken from the finished part rather than from the drawing. Its purpose is narrow and important: to show that the critical dimensions match the drawing revision you ordered against.
What to look for:
- The drawing or part number and revision stated on the report, matched to your PO.
- Each listed characteristic with nominal value, tolerance and measured value β not a pass/fail tick alone.
- Number of pieces measured and the batch or lot they belong to.
- Date of inspection and the identity of the inspector or inspection station.
A report that lists only "dimensions OK" tells you nothing you can audit. Ask for the measured values. If you need to know the measurement uncertainty of the CMM used, or how many pieces per lot are sampled, confirm with the supplier β sampling plans should be agreed in writing rather than assumed.
2. Hardness test data
Raceway hardness determines how a bearing or rail behaves under load and over time, and it is the property most often taken on trust. Hardness data turns that trust into a number.
For the materials commonly used in this product range, the specification bands are:
- LM bushings in GCr15: 60β64 HRC on the raceway.
- 55# steel guideway rails: 58β62 HRC.
Read the report for the test method, the location of each measurement (raceway versus core), the number of readings per part and which parts were tested. A single reading on one sample from a large lot is weak evidence; a set of readings across the batch is not. Where your application is sensitive to case depth or hardening process, ask the supplier which method was used and whether that data is available.
3. Lead accuracy report for ball screws
For ball screws, dimensional inspection of diameter and length is not enough β the lead accuracy class is what determines positioning behaviour. The report should state the class and the measured deviation over the defined length.
| Ball screw type | Accuracy class | Lead deviation |
|---|---|---|
| SFU rolled ball screw | C7 | Β±0.05 mm per 300 mm |
| SFE ground ball screw | C5 | Β±0.008 mm per 300 mm |
Values as specified for these series; confirm the applicable class and measurement length on the report for your order.
Check that the report names the series, the nominal diameter and lead, and the length over which the deviation was measured. A ground screw and a rolled screw are not interchangeable at the specification level, so the class on the report must match the class on your PO. For ground screws in particular, see the SFE series ground ball screw assembly for the series context.
4. Material certificates
A material certificate ties the finished part back to the steel it was made from. This is the document that makes batch traceability possible, and it is the one buyers most often forget to request.
It should identify the steel grade and, where applicable, the heat number or mill certificate reference. Grades relevant to this product range include GCr15 for bearing steel, 55# steel for guideway rails, and 9Cr18Mo for stainless bearing applications. Match the grade stated on the certificate to the grade specified for the part β a correct certificate for the wrong grade is still a non-conformance.
For heavy-duty rail applications, where the rail is the structural element, hardness and material data should be read together with the dimensional report. The HGR series heavy-duty linear guideway rail page gives the series background for these checks.
5. Third-party verification
In-house reports are produced by the same organisation that stands to benefit from a pass. Third-party verification, such as an SGS material report, exists to reduce that conflict. It typically covers material composition or specified properties on a sampled basis, and it is arranged per order rather than included by default.
When reviewing third-party documents, check that the report references your material batch, states the scope of what was tested, and is current for the shipment in question. A third-party report on a different batch is a reference document, not a substitute for your own batch records.
How to read the documents together
No single document closes the loop. The package works as a chain:
- The material certificate establishes what the part is made of.
- The hardness data establishes how that material was treated.
- The CMM report establishes whether the finished geometry matches the drawing.
- The lead accuracy report establishes positioning behaviour for ball screws.
- Third-party verification independently confirms part of the above.
A common failure mode is a package where each document is individually satisfactory but the batch or heat numbers on them do not match each other. Cross-check the identifiers first, then the values. That single habit catches most documentation problems before they become receiving disputes.
What to check on incoming goods
Documentation review and physical receiving should happen together.
- Labels against the PO. Part number, series, quantity and batch or lot number on the carton label should match the PO and the inspection package.
- Batch traceability. The lot number on the goods should lead back to the inspection reports and the material certificate. If it does not, ask for the missing link in writing.
- Drawing revision. Confirm the revision on the CMM report matches the revision you are actually building to. Revision drift is silent and expensive.
- Document completeness per shipment. Treat a missing report the same as a missing part β it blocks acceptance.
- Packaging condition. Record any transit damage against the batch number so it can be separated from manufacturing non-conformances.
A supplier who cannot produce measured values, only pass stamps, is telling you something about their process control. Ask for a sample full package before placing the first order.
Questions to ask any supplier before ordering
- Which documents are included in the standard outgoing package, and which are only available on request?
- Will the CMM report show measured values or only pass/fail, and against which drawing revision?
- What sampling plan applies to dimensional and hardness inspection for my order quantity? (Agree it in writing; do not assume a default.)
- Is the material certificate traceable to the specific heat or batch in my shipment?
- Is third-party verification available for this order, and which properties would it cover?
- For ball screws, which accuracy class will be documented, and over what measurement length?
- What is the warranty period, and what documentation is required to support a claim?
Frequently asked
Is a certificate of conformity enough?
It confirms the supplier declares the goods conform, but it does not give you measured values or traceability. For critical applications, pair it with the dimensional, hardness and material records.
Can I specify my own drawing for the CMM check?
Yes β supply the drawing and revision with the enquiry, and confirm that the report will reference that revision. Where tolerances differ from the standard series, discuss them before the order is confirmed.
Where do I find torque or mounting specifications?
Refer to the datasheet for the specific series, or confirm with the supplier for your configuration. Mounting torque depends on the rail size and bolt grade, and should not be taken from a generic table.
The short version. Specify the document package in the PO, cross-check batch identifiers before values, and treat documentation as part of the deliverable. Linear bearing inspection is only meaningful when the paper trail lets you verify the part in front of you.
Xiamen Dongfeng Bearing supplies linear motion bearings, guideways and ball screws with outgoing inspection documentation β CMM reports, hardness data and material certificates β plus ISO 9001 certification and a 24-month warranty; the standard document package is confirmed on your order, and third-party verification can be arranged per order. Product details are available at dflinear.com.cn.